TrainHy-Prof Workpackage 4

Person Month Distribution of Staff Effort per Workpackage
Work Package Title:  Implementation
Start date:  M6
Activity type:  SUPP
Work Package Leader:  JUELICH
Participant no:  1 2 3 4
Participant acronym:  JUELICH RISOEDTU ULSTER HELIO
Person Month:  2 1 1 1

Objectives

·   To implement elements of the course system designed in WPs 2 & 3 for a first trial run.
·   to liaise with the project on FCH education (SP1-JTI-FCH.2009.5.2: Training Initiatives for Regulators).

Description of work

WT 4.1: Course Programme (RISOEDTU, JUELICH, ULSTER, HELIO)

Establishment of the programme elements to be realised according to the curriculum (WP 2):

·   lecture titles and duration
·   lecturer recruitment
The course elements will include a summer school of new type (cf. WT 2.1) and some distance learning modules. Due to the limited resources, it will not be possible to run a 'complete' course as designed by the consortium.

WT 4.2: Written Lecture Material (HELIO, JUELICH, RISOEDTU)

Set up of the organisational programme:

·   location(s) & accommodation identification & booking
·   lecturer input
·   course material preparation
·   lecturer travel & expenses, budget & finance
as necessary for conducting the course elements according to WT 4.1. The task will build on the extensive experience of the consortium members in organising the SOFC summer schools, the FCH academy and the Hydrogen Safety courses.

Milestones and expected results

Milestone
number
Milestone
name
Work package(s)
involved
Expected
date
Means of
verification*
MS3 All organisational matters fixed for first course WP4, WP5 M8  
MS4 Lecturer roster completed WP4, WP2 M8  
MS7 First Course implemented and operational WP4, WP2, WP3, WP5 M10  
*In most cases the milestone verifies itself, by a statement 'documents available/received', meeting held, decisions taken etc. Only in the cases where this is not so, a specific action is given.

Deliverables

Deliverable
number
Deliverable
name
Work package
number
Access
level
Dissemination
level
Delivery
date
D4.1 First Run of Course WP4 O PU M10-21
CO = Consortium
RE = Consortium + Assoc. Groups + FCH JU + EU
PU = General public release
*Due to IPR protection constraints the materials themselves will only be available on a cost basis and be copyrighted by the Consortium.




File translated by Arief Dahoe from TEX using TTH, version 3.68.
On 18 Dec 2010, 06:45.